Holtec International
Profile
Holtec International is a privately held supplier of spent-fuel storage and transport systems and a decommissioning contractor that acquired the shut-down Palisades plant in Michigan from Entergy in 2022 and is pursuing its restart with DOE loan support, alongside two SMR-300 units (Palisades 'Pioneer') for which a phase-1 construction permit application with limited work authorisation was accepted for NRC review in February 2026 (final SER/EIS expected March 2027). Hyundai E&C is its EPC partner. Palisades is still listed as permanently shut down in the reactor dataset (PRIS); the restart date is a gap. Private; no market data apply.
Source: ExchangeMonitor 9 Jul 2026; the SMR projects dataset (NucNet 25 Feb 2026); the reactor dataset, 9 Oct 2026 · confidence mediumKey projects
| Project | Country | Stage | Note | Map |
|---|---|---|---|---|
| Holtec SMR-300 (Pioneer Units 1 and 2) - Palisades site, Covert Township, Michigan | USA | Licence application | Regulator stage as of 9 Oct 2026: Phase-1 construction permit application with limited work authorization submitted Jan 2026 (Federal Register 22 Jan 2026); NRC accepted part 1 for review Feb 2026; final SER/EIS expected Mar 2027 | open on the map |
| Palisades | USA | Restart planned | Not restarted as of 9 Jul 2026: turbine on turning gear, new fuel-handling machine installed, '>5,000 individual work activities still remain', no target date (ExchangeMonitor); PRIS still lists permanent shutdown 20 May 2022 | open on the map |
Deals
| Date | Type | Deal | Status | Capacity MW | Value |
|---|---|---|---|---|---|
| 30 Aug 2026 | Restart | Holtec begins fuel loading at Palisades ahead of first-ever US restart of a decommissioned plant | Pending | 800 | n/a |
| 15 Sep 2025 | Policy | UK and US announce Atlantic Partnership for Advanced Nuclear Energy ahead of Trump state visit | Signed | n/a | n/a |
| 24 Jul 2025 | Licensing milestone | NRC approves Palisades' transition from decommissioning back to an operating licence | Completed | 800 | n/a |
| 30 Sep 2024 | Financing | DOE closes USD 1.52 billion loan guarantee for Holtec's Palisades restart | Signed | 800 | 1.52 bn USD |
Documents
| Document | Type | Date |
|---|---|---|
| NucNet: US regulator accepts partial construction permit application for Palisades SMRs | News | 25 Feb 2026 |
| ExchangeMonitor: Palisades inches closer to restart with big projects completed, Holtec says | News | 9 Jul 2026 |